On December 5, 2024, EliTe Solar's high-efficiency cell production facility in Indonesia was successfully put into operation.
In May 2024, EliTe Solar decided on the location of the new plant after a careful site selection and evaluation process. in June, EliTe Solar quickly started the preparation of the equipment, which marked the beginning of the project implementation. In July, the construction of the project entered into a substantial construction phase with the official start of the civil works, which is the step that ensures that the subsequent work will be carried out smoothly. This step is the basis for ensuring that the subsequent work is carried out smoothly.
In September, a professional electromechanical installation team was officially stationed at the construction site. The task of the EliTe Solar team was to ensure that all infrastructure and production equipment would be accurately interfaced and that the installation and commissioning work would be carried out in an orderly manner. The precise execution of this phase is crucial for the quality and efficiency of the entire project.
In October, process equipment began arriving on site and being installed, and the completion of this step meant that the project was nearing completion.
Source:https://mp.weixin.qq.com/s/xbTc7PWY29e4LxwVC-z9ag