According to EnergyTrend, on November 23, the Ecological Environment Bureau of Chuzhou City, Anhui Province issued the " Zhongrun New Energy (Chuzhou) Co., Ltd. High-efficiency large-size photovoltaic cell technical transformation project Ecological Environmental Impact Report" is published before approval, and approval opinions are planned for the project.
According to the announcement, the project is located in the west section of Lu'an Road, Economic Development Zone, Langya District, Chuzhou City, with the factory covering a total area of 724 acres. This technical transformation mainly targets the technical upgrade of the production lines and ancillary facilities of the two existing production workshops. After the technical transformation, high-efficiency large-size photovoltaic cells will be produced without adding new factories, infrastructure or production capacity.
It is understood that the original 16 GW high-efficiency photovoltaic cell project of Zhongrun Solar's Chuzhou base was constructed in two phases, with each phase having a capacity of 8 GW. The independent completion environmental protection acceptance was completed in August 2023 and February 2025 respectively. The total investment in this technical transformation is about RMB 800 million, which mainly involves the upgrading of the production lines of two major workshops: Among them, the battery workshop 1 is planned to Transform the existing 16 TOPCon production lines into TBC production lines; Battery Workshop 2 introduces processes such as back laser, edge passivation and silver-coated copper. Upgrade the existing TOPCon production line.
This environmental impact assessment has entered the pre-approval publicity stage, which means The approval process for the 16 GW battery production line technical renovation project at SolarSpace’s Chuzhou base is further advanced. After the technical transformation is completed, SolarSpace will further adjust the technical structure of the existing battery production line.
Source:EnergyTrend